Kitimat's second LNG train clears environmental review

The certificate carries forty-one conditions, and the two that matter most are about electricity.

The loading berth at Kitimat, between sailings.
The loading berth at Kitimat, between sailings. Illustration for the Chronicle

The environmental certificate for the second liquefaction train at Kitimat was issued Thursday, forty-one conditions attached, and the project's fate now turns on the two conditions that read least like environmental language: the ones about where its electricity comes from.

The expansion is approved on the basis of grid power — the design that keeps its emissions inside the province's cap. The certificate requires an executed supply agreement before construction and gives the utility's next capacity call a named role in the schedule, which is the first time a north coast industrial certificate has tied itself so explicitly to a transmission queue.

The catch is the queue itself. The northwest transmission line is already spoken for several times over — mines in the golden triangle, the port's electrification, and now this — and the utility's own filings put new capacity on the coast years behind the project's preferred schedule. Gas-fired backup would fit the timeline and break the emissions math; the certificate, read closely, forbids exactly that resolution.

The company's statement welcomed the decision and said nothing about sequencing. The town, which has been through one construction boom and knows the shape of the next one, mostly asked practical questions at Thursday's open house: which camp, which road, and whether the airport gets its instrument approach before the flights double again.